Site: ______________________ Date: ____________ Checked by: ______________________
01Permit and planning
02Support
03Edges and surroundings
04Access and air
05Inspection
Legal requirement
Under Singapore's Construction Regulations 2007, excavations deeper than 1.5 metres need shoring unless a professional engineer certifies them safe. Over 4 metres, a PE designs and certifies the shoring. Open sides deeper than 2 metres need guard-rails. A designated person inspects after every rainstorm. Excavation and trenching deeper than 1.5 metres on a worksite need a permit-to-work from the project manager.
Sources and further reading
- Workplace Safety and Health (Construction) Regulations 2007, Singapore Statutes Online (AGC).
- Code of practice on safety and health in construction (revised 2022), International Labour Organization.
This is practical guidance, not legal advice. Laws and codes of practice change; always check the current official text and your site's own procedures.