Site: ______________________ Date: ____________ Checked by: ______________________
01Design and paperwork
02Base and shores
03Bracing and connections
04Deck, edges and access
05Before and during the pour
06Striking and reshoring
Legal requirement
Under Singapore's Construction Regulations 2007, formwork must carry all loads with a safety factor of at least 2, and a trained formwork supervisor must be present whenever it is erected, altered or struck. Formwork over 9 metres high, with shores in two or more tiers, or casting slabs or beams over 300 mm thick, must be designed by a PE and certified before use. No concrete goes into PE-designed formwork until the PE has inspected and certified it.
Sources and further reading
- Workplace Safety and Health (Construction) Regulations 2007, Singapore Statutes Online (AGC).
- Advisory for professional engineers on formwork safety (January 2014), Ministry of Manpower.
- Code of practice on safety and health in construction (revised 2022), International Labour Organization.
This is practical guidance, not legal advice. Laws and codes of practice change; always check the current official text and your site's own procedures.